Also read Why You Should Manage Project Risks | Risk Analysis | Risk Assessment | Challenges in Risk Evaluation and Risk Response.
There are primarily two aspects of risk evaluation / risk assessment:
Risk assessment is subjective to greater extent but with properly established policies, guidelines and practices it can be standardized to greater degree. Based on above two aspects, the rating for a given risk can be determined.
Rating |
Description |
Likelihood of Occurrence |
1 |
Rare |
Risk occurrence is highly unlikely.Exceptionally it may occur, but most likely it will never occur |
2 |
Unlikely |
The risk occurrence is not expected. But in slight probability, it may occur |
3 |
Possible |
This risk may occur some times as organization has observed historical trace of such risks |
4 |
Likely |
This risk has strong possibility of occurrence as organization has frequently observed trace of such risks |
5 |
Almost Certain |
This risk is most likely to occur. The instance/incidence is expected to occur in speculated timeframe as organization has observed trace of regular occurrence of such type of risks |
Table 1: Probability of Risk
The severity of the potential loss, if risk occurs is the second parameter of risk assessment. Again, this parameter is highly contextual. When team members register a risk, he/she may not have the complete idea of the situation. Hence project planner or manager is expected to take the context into consideration and determine the consequence of the risk if occur in future. Based on the learning from previous risks/history, organization may create a reference or guideline to determine severity of the risk. Project planner/manager refers such guideline and uses his/her judgment to determine the consequence of the risk in consideration as a part of risk assessment process.
Rating |
Description |
Example to illustrate |
1 |
Insignificant |
Minimal project delay| loss; Less than a week| < few hundred $ |
2 |
Minor |
Minor project delay | loss; more than 3 weeks| $100k< x <$10k |
3 |
Moderate |
Moderate project delay| loss; more than 12 weeks | $1M<x<$100k |
4 |
Major |
Major project delay| loss; More than 2 month | $1M<x<$100k |
5 |
Catastrophic |
Intolerable project delay| loss; More than 6 month | $x >$5M |
Table 2: Consequence of risk
Based on probability of occurrence of risk and potential severity that it may cause, project managers can derive the rating the risk. Organizations with good project risk management practice have escalation guidelines based on the project risk rating. Which specifies what escalation matrix should be used depending on the rating of the risk.
The table below gives indicating ‘Required Action’ based on the rating of a risk. Your organization will have different required action or escalation matrix based on your industry/organization’s practices.
Rating |
Required Action |
Low |
Acceptable: Not mandated to deploy additional resources; Such risk is expected to be managed through normal routine. Action:Track and review |
Moderate |
Acceptable:Such risk is not expected to cause much damage or jeopardize the overall objective or effectiveness of project Action: Project Manager to create a response plan.Track and Respond. |
High |
Not Acceptable to larger extent: Such a risk is highly likely to cause considerable damage or jeopardies overall project objective or effectiveness. |
Extreme |
Not Acceptable at all :Such a risk is extremely likely to pose as a threat to the continuation/functioning of a project/ organization. |
Table 3: Risk Rating
As mentioned earlier, the organization as a whole need to assess these parameters, significance of each parameter and required action i.e. a meaningful guideline to perform risk assessment to state a given risk having ‘Major’ severity with what probability as ‘Likely’. Though ‘Likely’, ‘Extreme’, ‘Moderate’, ‘Catastrophic’ are generic terms, the resource who will work with reference to these terms need to understand clearly, what they need to do with it.
Let me know how you find this post. I would love to hear your feedback.
Also read Why You Should Manage Project Risks | Risk Analysis | Risk Assessment | Challenges in Risk Evaluation and Risk Response.
_____________________________________________________________________________
Use project management software for project planning & scheduling - Try ZilicusPM a powerful tool that enable online project planning WBS, online scheduling, resource assignment, Gantt chart, project tracking, issue management, online calendar, risk register and much more.